Clients

Abco Supply & Service
1999-Instrument Installation for Canamera Foods at Harrowby, Manitoba

Abitibi Price Inc.
1987-Two paper machine upgrades at Thunder Bay, Ontario

Adam Clark Ltd.
1990-Instrument installation of Comp. Station for Trans Canada Pipelines at Hearst, Ontario
1990-Instrument installation of Comp. Station for Trans Canada Pipelines at Kapuskasing, Ontario

Aecon Group Inc.
2012-Instrument installation for Spectra Energy’s Sunset Comp. Stn. at Fraser Lake, B.C.

Alberta Pacific Forest Ind. Ltd.
1993-Calibration of Instruments for New Kraft Pulp Mill at Lac La Biche, Alberta

Albian Sands Energy
2003-Instrument Loop Checks and Commissioning Plant Wide at Ft. McMurray, Alberta

Alcan Canada Ltd.
1989-DC4 Die Casting package
1989-H.V. Control System Kemano, B.C.

Alliance Brewing Company
1995-Instrument Audit and Supply for Five Star/3 Ring Breweries at Beijing, China

Alliance Energy
1997-Instrument Installation for Prairie Malt Expansion at Biggar, Saskatchewan
1996-Instrument Installation for Prairie Malt Phase II Expansion at Biggar, Sask.

Apple Electric
2019 – Instrument Installation for the Comox Valley Regional District’s Biosolids Facility Expansion at Comox, B.C.

Archie Johnstone Plumbing
2019 – Instrument Installation for BC Transit’s Victoria TC Waste Water Treatment Plant at Victoria, B.C.

Argo Industrial
1997 – Instrument Installation for Huckleberry Mines north of Houston, B.C.

Argus Installations Ltd.
1980- -Instrument installation for Westcoast Transmission at Summit Lk., Hixon, and Vanderhoof B.C.

Associated Kellogg Ltd.
1982-Control cabinets for Strathcona Refinery Burnaby, B.C.

ATCO Power/SaskPower Corp.
2003-Instrument Loop Checks and Commissioning for Brighton Beach Power Project at Windsor, Ontario
2002-Instrument Installation and Commissioning for Cory Cogeneration Power Plant At Saskatoon, Saskatchewan

B.C.Chemicals Ltd.
1990-Cost Plus Instrument Installation at Prince George, B.C.

BC Forest Products Ltd.
1984-Instrument installation on the backhoe drying system at Crofton, B.C.
1980-Control panel for Turbogenerator, Crofton, B.C.

Bechtel Canada Ltd.
1991-Instrument Installation for Husky Bi-Provincial Upgrader Plant 42 at Lloydminster, Sask.

BFC Industrial
1997-Instrument Installation for EB Eddy Forest Products Hardwood Modernization at Espanola, Ontario

Birwelco Ltd.
1987-G.V.R.D. incinerator package at Burnaby, B.C.

Black and McDonald
2013-Instrument Installation for Calgary Airport Authority’s Trail Tunnel Project in Calgary, Alberta

Boise Cascade Canada Ltd.
1991-R8 Module Instrument Installation at Fort Frances, Ontario
1986-Instrument installation of effluent monitoring system at Kenora, Ontario
1985-Supply of control panels and installation of Digester at Ft.Frances, Ontario

Brymark Installations
2019-Instrument Installation for Fortis’ LMIPS Coquitlam Gate Station at Coquitlam, B.C.
2013-Instrument Installation for Air Liquide’s NS Phase 3 Project at Dawson Creek, B.C.
2012-Instrument Installation for Air Liquide’s LIN Production Project at Dawson Creek, B.C.
2004-Instrument Installation for Chevron Canada’s LSP Project at Burnaby, B.C.

Campbell Cox Ltd.
1999-Instrument and Tubing Installation for Transcanada Pipelines Ltd. at Burstall, Saskatchewan

Campbell Red Lake Mines Inc.
1987-Instrument installation of mine upgrade Red Lake, Ontario

Cana Construction Ltd.
1992-Instrument Installation for MacMillan Bloedel Ltd. on Secondary Effluent Project at Port Alberni, B.C.

Canadian Energy Services Ltd.
1989-Canadian Energy Services Ltd.
1989-Boiler rebuild at Fletcher Challenge Canada McKenzie, B.C.
1989-Recovery Boiler installation Fletcher Challenge Canada Ltd., McKenzie,B.C.

Canadian Forest Products Ltd.
1988-Numerous small projects, at Port Mellon, B.C.
1987-Numerous small projects, Port Mellon, B.C.
1986–Instrument installation of paper machine Port Mellon, B.C.
1985-Cost Plus upgrade of Oxygen system Port Mellon, B.C.
1982-Instrument installations, Port Mellon, B.C.
1982-Control panels, Port Mellon, B.C.
1981-Control panels, Port Mellon, B.C.

Canadian Liquid Air
1984-Instrument installation at Edmonton, Alta.

Canadian Pacific Forest Products Ltd.
1991-Re-Instrumentation of Power Boiler at Gold River, B.C.

Canexus Chemicals
2010-Instrument Installation and Commissioning For Chemical Plant At N.Vancouver, B.C

Canfor – P.G.Pulp and Paper Ltd.
1990-Cost plus Instrument installation for DCS at Pr.George, B.C.
1990-P.L.C. & Marshalling Cabinet Supply for DCS Stage 5 at Prince George, B.C.

Cariboo Pulp and Paper Ltd.
1991-Instrument Installation for Oxygen Delignification Project at Quesnel, B.C.

Casca Electric Ltd.
2008-Instrument Installation for Suncor’s MCU Cooling Tower at Ft McMurray, Alberta
2008-Instrument Installation & Commissioning for Petro Canada’s Refinery Conversion Project at Edmonton, Alberta
2005-Instrument Installation for Petrocan’s G.O.T. Project at Edmonton, Alberta
2004-Instrument Installation for Suncor’s Millenium Vacuum Unit at Ft. McMurray, Alberta
2001-Instrument Installation for Suncor’s TEC Project at Ft.McMurray, Alberta
1997-Instrument Installation for Suncor C601 Extraction Expansion at Ft. McMurray, Alberta

Centec Electric
2019-Instrument Supply for Koch’s New CCR/Maintenance Shop at Brandon, Manitoba
2016-Instrument Installtion for Koch’s 101J Compressor Project at Brandon, Manitoba
2015-Instrument Installation For Enbridge at Numerous Stns in Manitoba
2014-Instrument Installation For Enbridge at Numerous Stns in Saskatchewan & Manitoba
2013-Instrument Installation For Bunge Canada Seed & Meal at Altona, Manitoba
2013-Instrument Installation For Enbridge at Numerous Stns in Saskatchewan & Manitoba
2011-Instrument Installation For Vale Inco’s Water Treatment Plant At Thompson, Manitoba
2010-Instrument Installation For City of Neepawa Waste Water Treatment Plant At Neepawa, Manitoba
2008-Instrument Installation for Maple Leave Foods Wastewater Treatment Plant at Brandon, Manitoba
2008-Instrument Installation on for Canexus Phase VII Expansion at Brandon, Manitoba
2006-Instrument Installation on PMU Plant for Ayerst Organics at Brandon, Manitoba
2004-Instrument Installation for Wyeth Ayerst Plant B at Brandon, Manitoba

Cerro Verde
1995-Electrical/Instrument Material Estimate and Supply for Fluor Daniel Wright at Arequipa, Peru

Chemco Electrical
2002-Instrument Installation and Commissioning for ATCO Power Muskeg River Co-Gen Plant at North of Ft. McMurray, Alberta
2001-Instrument Installation for Suncor Ore Preparation Plant At Fort McMurray, Alberta
1997-Instrument Installation for Raylo Chemicals at Edmonton, Alberta

Chemcon Installations Ltd.
1995-Instrument Installation on malt plant for Prairie Malt Co. Ltd. at Biggar, Saskatchewan

Chevron Canada Ltd.
2014-Cost plus instrument installation and calibration Burnaby, B.C.
1986-Cost plus instrument installation and calibration Burnaby, B.C.
1985-Cost plus instrument installation and calibration Burnaby, B.C.

City of Atikokan
1998-Instrument installation at Water Treatment Plant Atikokan, Ontario

Cominco Inc.
1987-Manufacture of Pneumatic Valve Panels
for Red Dog Mine at Anchorage, Alaska

Comstock Canada
2009-Instrument Installation For the City of Winnipeg’s Deacon Water Treatment Plant At Winnipeg, Manitoba
2007-Instrument Installation and Commissioning for ALPC Opti-Nexen SAGD Mine at Ft.McMurray, Alberta
2006-Instrument Installation and Commissioning CC705 for Syncrude Canada Ltd. at Ft.McMurray, Alberta
2006-Shutdown Work on S5164 for Syncrude Canad at Ft. McMurray, Alberta
2003-Instrument Installation on CC705&CC707 for Syncrude Canada Ltd. at Ft.McMurray, Alberta
2001-Instrument Installation for Pine Falls Paper TMP Plant at Pine Falls, Manitoba
2000-Instrument Installation & Commissioning for Weyerhaeuser Canada BFB Project At Pr. Albert, Saskatchewan
2000-Instrument Installation & Commissioning for Alliance Pipelines At Kerrobert, Estlin, Alameda, & Loreburn Saskatchewan
2000-Instrument Installation & Commissioning for Alliance Pipelines At Blueberry Hill, Alberta
1999-Instrument Installation on Recovery Boiler for Weyerhaeuser Canada Ltd. at Pr. Albert, Saskatchewan
1999-Instrument Installation on Washer Press for EB Eddy Forest Products at Espanola, Ontario
1998-Instrument Installation on Nitric Acid Plant, Urea Plant, & Urea Granulation for Simplot Canada at Brandon, Manitoba
1998-Instrument Installation on Hardwood Modernization Project including Bleach Plant and Stripper for EB Eddy Forest Products at Espanola, Ontario
1997-Instrument Installation for Weyerhaeuser Canada NCG Plant at Pr. Albert, Saskatchewan
1997-Instrument Installation for Tantalum Mines Corp. at Lac Du Bonnet, Manitoba
1997-Instrument Installation for Simplot Canada Ammonia Plant Ammonia Storage, and Utilities at Brandon, Manitoba
1997-Instrument Installation for Algoma Steel Expansion at St. Ste. Marie, Ontario
1996-Instrument Installation on New De-Inking Plant for Pine Falls Paper Company at Pine Falls, Manitoba
1996-Instrument Installation on New TMP for Abitibi-Price Inc. at Iroquois Falls, Ontario
Comstock Canada Constructors Ltd.
1995-Instrument Installation for Placer Dome Mines Inc. at South Porcupine, Ontario
Comstock Canada Constructors Ltd.
1995-Instrument Installation on Secondary Effluent Package for Abitibi-Price Inc. at Iroquois Falls, Ontario
Comstock Canada Constructors
1995-Instrument Installation for Transgas Ltd. at Rosetown, Saskatchewan
1993-Instrument Installation for Dow Chemicals Canada Ltd. on Water Treatment Project at Fort Saskatchewan, Alberta
1993-Instrument Installation for Alberta Pacific For. Ind. on Power Group, Recaust, Woodroom at Lac La Biche, Alberta
1993-Instrument Installation for Ayerst Organics Ltd. on New PMU Plant at Brandon, Manitoba
1992-Instrument Installation for Hudson Bay Mining & Smelting Flin Flon, Manitoba
1990-Instrument installation of Comp. Station for Trans Canada Pipelines at Cornwall, Ontario

Corewest Fabrications Ltd.
1985-Supply and installation of instruments on skids for Moli Energy Ltd. Coquitlam, B.C.

Daves Plumbing & Heating (1962) Ltd.
1983-Eurocan warm water recovery at Kitimat River Hatchery #8, Kitimat, B.C.

Delray Construction Ltd.
1984-Instrument installation at the Kitimat River hatchery at Kitimat, B.C.

Delta Catalytic Ltd.
1996-Instrument Installation on SPX Project for Repap Manitoba at The Pas, Manitoba

Derksen Mechanical
2004-Instrument Installation for Nexen’s Phase 4 Expansion at Brandon, Manitoba

DMS Industrial
2019-Instrument Installation for Manitoba Hydro’s Voith Keeyask Generating Station near Gillam, Manitoba
2018-Instrument Installation & Commissioning for Hudbay’s Lalor Paste Plant at Snow Lake, Manitoba

Dominion Bridge Ltd.
1996-Instrument Installation on Digester for Fletcher Challenge Canada at MacKenzie, B.C.
1994-Instrument Installation on Incinerator for the University of British Columbia at Vancouver, B.C.
1991-Instrument Installation for Pacific Coast Energy Metering Stations at Vancouver Island Locations, B.C.
1991-Crystallizer Installation for Brandon Chemicals at Brandon, Manitoba
1989-Sodium Chlorate installation for Canadian Oxy at Brandon, Manitoba

Domtar Chemical Group
1985-Supply and installation of control room New Westminster, B.C.

Dual Mechanical
2015-Installation and Control Panel Supply for Translink’s Hamilton Transit Centre in Richmond, B.C.

E3 Services Ltd.
2003-Instrument Installation for Suncor Canada’s NRU Project at Ft. McMurray, Alberta

E.S.Fox Ltd.
2007-Instrument Installation & Controls Upgrade for Ontario Power at Thunder Bay, Ontario
2002-Instrument Installation for TransAlta Utilities Co-Generation Plant at Sarnia, Ontario
2000-Instrument Installation & Commissioning for Weyerhaeuser OSB 2000 Project At Hudson Bay, Saskatchewan
1999-Instrument Installation on Feedwater Plant for James River Marathon at James River, Ontario
1999-Instrument Installation on Mine at Agrium Inc. at Kapuskasing, Ontario
1996-Numerous Instrument and Hydraulic Tubing Installations for the Clarifiers and #3 Winder for Stone Consolidated Corp. at Fort Frances, Ontario

Elgar Electric
2009-Instrument Installation For False Creek Energy Centre At Vancouver, B.C

Eurocan Pulp and Paper Ltd.
2007-Instrument Installation for Steam Turbine Power Plant at Kitimat, B.C.
1994-Instrument Installation and Calibration on Numerous Projects at Kitimat, B.C.
1993-Instrument Installation for Numerous Projects at Kitimat, B.C.
1992-Instrument Installation on Numerous Projects at Kitimat, B.C.
1989-CMP, Paper Machine, Digester and others Kitimat, B.C.
1988-Re-Instrumentation of Digester, at Kitimat, B.C.
1987-Paper machine upgrade, Kitimat, B.C.

Equity Silver Mines Ltd.
1981-Wiring of operating panels, Houston, B.C.

F.& M Installations
2015-Instrument Installation For BC Hydro’s Mica Dam Units #5/6 north of Revelstoke, B.C
2011-Instrument Installation and Commissioning For Neucel Pulp’s Evaps and Boiler At Port Alice, B.C.
2010-Instrument Installation and Commissioning For BC Hydro’s Revelstoke Dam Unit #5 At Revelstoke, B.C
1990-Boiler Rebuild for Canadian Pacific Forest Products at Gold River, B.C.
1989-Pulp Mill rebuild at Fletcher Challenge Canada Crofton, B.C.

Finlay Forest Industries Ltd.
1998-Instrumentation Maintenance for complete pulp mill at Mackenzie, B.C.

Flanders Installations Ltd.
1981-Instrument Installation, Northwood Pulp & Paper Pr.George, B.C.

Foundation Co. of Canada Ltd.
1994-Instrument Installation of Recaust for Crestbrook Forest Industries at Skookumchuk, B.C.
1989-Installation of complete Pulp Mill for Daishowa Canada Ltd. at Peace River, Alberta
1988-Quesnel River Pulp TMP and CTMP expansion Quesnel, B.C.
1988-Instrumentation on complete mill Quesnel River Pulp Ltd., at Quesnel, B.C.

Gifford Electric
2019-MetroVancouver’s Queensborough PS Flowmeter Project at Richmond, B.C.

Gisborne Construction
2005-Steam Tracing For Husky Oil’s Clean Fuels Project. at Prince George, B.C.

Gotaverken Energy Systems Ltd.
1989–Recovery Boiler installation Cariboo Pulp and Paper Ltd., Quesnel, B.C.

Graham Construction
2018-Instrument Installation for Gilead Pharma’s API Process Tower at Edmonton, Alberta
2018-Instrument Installation for Cameco’s Freeze Plant #3 at Cigar Lake, Saskatchewan
2016-Instrument Installation for Areva’s Tailings Neutralization Project at McLean Lake, Saskatchewan
2015-Instrument Installation for Areva’s JEB Mill Upgrade Project at McLean Lake, Saskatchewan
2015-Instrument Installation For Syncrude’s Mildred Lake Pant 13.1 at Ft. MacMurray, Alberta
2014-Instrument Installation for SaskPower Corp’s Shand CCTF-450 Pilot Plant Project at Estevan, Saskatchewan
2013-Instrument Installation for SaskPower Corp’s Boundary Dam at Estevan, Saskatchewan
2012-Instrument Installation for Mosaic Potash’s CE650 at Colonsay, Saskatchewan
2012-Instrumentation Installation for Potash Corp of Sask. Prod. Loadout at Rocanville, Saskatchewan
2011-Instrument Installation and Commissioning For SaskPower’s Queen Elizabeth Power Station At Saskatoon, Saskatchewan
2009-Instrument Installation and Commissioning For SaskPower’s Power Generation Project At Kerrobert, Saskatchewan
2008-Instrumentation Installation for Potash Corp of Sask. Rehabilitation Project at Lanigan, Saskatchewan
2006-Instrumentation Installation on Ethanol Plant for Husky Energy at Lloydminster, Saskatchewan
2004-Instrument Installation for Potash Corporation of Saskatchewan’s Expansion at Rocanville, Saskatchewan
2002-Instrument Installation for SaskPower Corp’s Queen Elizabeth Power Stn at Saskatoon, Saskatchewan

Great West Electric
1999-Instrument Installation for Power Co-Generation Plant At Ft. Nelson, B.C.
1997-Instrument Installation for Placer Dome Mines at Musselwhite, Ontario

G.V.R.D.
1987-Steam and condensate lines, Burnaby, B.C.

H.A.Simons (International) Ltd. 
1981-Control panels for Northwood Pulp and Paper Ltd. Pr.George, B.C.

H.A.Simons (Overseas) Ltd.
1980-Relay panels for Ruzomberok, CSSR

Houle Electric Ltd.
2019-Instrument Installation and Control Panel supply for the City of Ashcroft’s Water Treatment Plant at Ashcroft, B.C.
2018-Instrument Installation on Acid Plant #2 for Teck Metals at Trail, B.C.
2018-Instrument Installation on West Line Creek Mine for Teck Metals at Sparwood, B.C.
2017-Instrument Installation and Commissioning for Howe Sound Pulp’s O2D Project at Port Mellon, B.C.
2017-Instrument Installation and Commissioning for Howe Sound Pulp’s O2 Compressor Project at Port Mellon, B.C.
2015-Instrument Installation on WP#19 Dynamic Test Facility for Dept. of Nat. Defense in Esquimalt, B.C.
2015-Instrument Installation on South Fork Water Tmnt. Plant in Nanaimo, B.C.
2015-Instrument Installation on Sleeman’s Brewery Expansion in Vernon, B.C.
2013-Instrument Calibrations and Installation for Cominco’s Acid Plant #1 in Trail, B.C.
2013-Instrument Calibrations and Installation for Reservoir for City of Nanaimo, B.C.
2012-Instrument Calibrations and Installation for Dept. of Nat. Defense’s WWTP at Esquimalt, B.C.
2003-Instrument Calibrations and Installation for Comox Biosolids Facility at Comox, B.C.
1995-Instrument Installation on TMP for Finlay Forest Industries at Mackenzie, B.C.
1988-Instrument installation for boiler at Finlay Forest Products, Mackenzie B.C.

Howe Sound Pulp and Paper
1991-Electrical and Instrumentation Commissioning Team on Brown Stock and TMP including Startup and Loop Checks. at Port Mellon, B.C.
1990-Generator Protection Switchboard Panel at Port Mellon, B.C.

Husky Energy 
2007-Instrument Supervision for New Ethanol Plant at Minnedosa, Manitoba

Imperial Oil Limited 
1981-Fabricate and install control consoles for Strathcona Refinery, Edmonton, Alta.

Interior Power and Chemical Ltd.
1988-Supply and installation of Instruments for #5 recovery boiler, Skeena Cellulose Pr.Rupert, B.C.

James River Paper
1996-Supply of Instrument/Electrical Field Control Panels for Evaporator Plant at Marathon, Ontario

Kamyr Construction Ltd.
1993-Calibration & Start-Up Assistance on Celgar Digester at Castlegar, B.C.

Kamtech Services Ltd.
2003-Numerous Mechanical Contracts for Weyerhaeuser Canada Ltd.’s New Recovery Boiler at Dryden, Ontario

KBV Shepard Power Partners
2015-Instrument Commissioning for Enmax at the Shepard Energy Centre Power Plant in Calgary, Alberta

KCI Construction Ltd.
2002-Instrument Installation for Willamette Industries Fibreline Project at Albany, Oregon USA

Keith Plumbing
2019-Instrument Installation For the University of Victoria’s District Energy Plant at Victoria, B.C.

Keldon Electric Ltd.
2010-Instrument Installation For RDNO’s Duteau Creek Water Treatment Plant At Vernon, B.C.
1994-Instrument Installation and Calibration for City of Kelowna Treatment Plant at Kelowna, B.C.

Key Lake Mining Corporation
1983-Instrument installation at Key lake, Sask.

Kiewit Industrial 
2006-Steam Trace Tubing for Husky Pils at Prince George, BC

Kimberley Clark 
1985-Power boiler rebuild at Terrace Bay, Ontario

Kinder Morgan 
2010-current-Numerous Maintenance projects at Vancouver Wharves in Vancouver, B.C.

KTI Fish Inc.
1998-Manufacture of Weep Hole Monitoring Cabinet for Simplot Canada at Brandon, Manitoba

Labatt Breweries of B.C. Ltd.
1999-Instrument Supply and Install for Steam Flow Transmitter Project at New Westminster, B.C.
1995-Instrument Maintenance and Service at New Westminster, B.C.
1994-Instrument Servicing and Installation on Numerous Projects at New Westminster, B.C.
1987-Numerous small projects, at New Westminster, B.C.

Lac Minerals Ltd.
1985-Power boiler rebuild at Terrace Bay, Ontario

Lakewood Electric Ltd.
1991-R8 Module Instrument Installation for Canfor – Intercon Pulp Mill at Prince George, B.C.

Lockerbie & Hole Cont. Ltd.
2013-CC109 Instrument Installation for Potash Corp. of Sask. at Rocanville, Sask.

MacMillan Bloedel Ltd.
1997-Instrument Installation on Controls Migration, Power Boiler #19, Steam Plant, and misc. areas
1996-Instrument Installation on Bleach Plant Upgrade at Powell River, B.C.
1987-Numerous Cost plus contracts, Powell River, B.C.

Magna Electric Corp.
2013-Instrument Installation on CC110 & CC111 for Potash Corp. of Sask. at Rocanville, Sask.

Martech Electrical Ltd.
2019-Instrument Installation on CP Rail’s Moose Jaw Waste Water Treatment Plant at Moose Jaw, Sask.
2008-Instrument Installation for Teck Cominco’s #4 Acid Storage Tank in Trail, B.C.
2005-Instrument Installation for Teck Cominco’s Re-leach Project in Trail, B.C.
2000-Instrument Installation for CFI Tembec Co-Gen At Skookumchuck, B.C.
1996-Instrument Installation on New LSP Project for Cominco at Trail, B.C.
1996-Instrument Installation on Co-Gen for ASD Joint Venture (Finlay Forest) at MacKenzie, B.C.
1994-Instrument Installation of Colour Clarifier for Crestbrook Forest Industries at Skookumchuk, B.C.

Methanex Fortier, Inc.
1994-Startup and Commissioning of Methanol Plant at New Orleans, Louisiana

Mitchells Installations Ltd.
1980-Control panel for Turbogenerator, Crofton, B.C.

Molson Breweries Ltd.
1995 to Current-Instrument Maintenance and Service at Vancouver, B.C.

Mott Electric
2006-Instrumentation Installation and Calibration for Greater Vancouver Water District at N.Vancouver, B.C.
2005-Supply of Switchgear Panels for Greater Vancouver Water District at N.Vancouver, B.C.
2004-Instrument Supply and Install for Greater Vancouver Water District Capilano Stn. at N.Vancouver, B.C.

Mueller Electric
2008-Instrumentation Installation & Commissioning for Taseko Mines Ph. III and SAG Mine at Williams Lake, BC

N.B.C. Mechanical Ltd.
1985-Furnace rebuild for Alcan at Kitimat works Kitimat, B.C.

Nesco Electric Ltd. 
1984–Instrument/Electrical installation Pulping Group The Pas, Manitoba

Neucel Specialty Cellulose
2007–Instrument Maintenance at Port Alice, BC

Nicholls Radtke Ltd.
1998-Instrument Installation on Dry Plant Loadout Facility for Omya at Perth, Ontario
1996-Instrument Installation for TCPL Co-Gen Plant at Kapuskasing, Ontario
1996-Instrument Installation for TCPL Co-Gen Plant at North Bay, Ontario
1991-Pneumatic tubing for T.C.P.L. Stn. #1401 at Iroquois, Ontario

Northwest Electric Ltd.
1986-Mine installation at Lynn Lake, Manitoba

Northwest Territories Power Corp.
1996-Supply of Electrical Control Panels ECP & LECP at Inuvik, N.W.T.

PCL Industrial Constructors Ltd.
1994-Instrument Installation on Foothills Pipelines Monchy Comp.Stn. at Val Marie, Saskatchewan
PCL Constructors Ltd.
1992-Instrument Installation for Husky Oil Bi-Provincial Upgrader Plant 21 at Lloydminster, Sask.
1983-Instrument installation at Keephills Generating Station, Edmonton, Alta.

Peterson Electric Ltd.
2001-Instrument Installation for North American Palladium at North of Thunder Bay, Ontario
2001-Instrument Installation for Bowater Recovery Boiler & Concentrators at Thunder Bay, Ontario
1997-Instrument Installation for James River Marathon Corp on Evaps at Marathon, Ontario
1996-Instrument Installation for Evaporator Plant for James River Paper at Marathon, Ontario
1992-Instrument Installation for James River Marathon’s Recovery Boiler Rebuild at Marathon, Ontario
1991-Instrumentation for Boise Cascade on the Sulphite Digester at Kenora, Ontario
1988-Mine revamp at Lac Minerals, Balmertown, Ontario

Placer Dome Inc.
1988-Instrument installation of Mill expansion South Porcupine, Ontario

Prep Energy
2019-Instrument installation for the Comox Valley Regional District’s Twin Cedars Waste Water Treatment Facility Upgrade Project at Cobble Hill, B.C.
2019-Instrument installation for the Klahoose First Nations’s Water System Improvements Project on Cortes Island, B.C.

Prince George Pulp & Paper Ltd.
1991-Instrument Installation for DCS Upgrade and Mill Revamp at Prince George, B.C.

Quality Rewind
2005-Instrument Installation for Albian Sands 3rd Tailings Project. at Ft. McMurray, Alberta

REES Electric
2011-Instrument Installation and Commissioning For Copper Mountain Mining At Princeton, B.C.

Reichhold Limited
1997-Current-Numerous miscellaneous service calls and projects in Port Moody, B.C.
1996-Instrument Installation on New Tank Farm at Port Moody, B.C.

Ridgeview Industrial Electric Ltd.
1999-PLC Panel for Cominco Ltd. at Trail, B.C.

Ross Morrison Electric Ltd.
2019-Instrument Installation For MetroVancouver’s Lulu Island Waste Water Treatment Plant Biogas Cleanup Project at Richmond, B.C.
2019-Instrument Installation For the City of Vancouver’s False Creek Energy Centre (NEU) Flood Re-Build Project at Vancouver, B.C.
2012-Instrument Installation For Harvest Power’s FRSF Biogas Project at Richmond, B.C.
2011-Instrument Installation For Lions Gate Waste Water Treatment Plant at North Vancouver, B.C.
2009-Instrument Installation for Vancouver Wharves C10008B Fuelling Project at Vancouver, B.C.
2008-Instrument Installation for Erco’s Hydrogen Recovery Project at North Vancouver, B.C.
2002-Instrument Installation for Imperial Oil at Vancouver, B.C.

S&S Electric Ltd.
2000-Instrument Supply and Install for Greater Vancouver Regional District At Langley, B.C.
1999-Supply and Install Instruments for GVRD NW Langley Wastewater Treatment Plant at Langley, B.C.

Safematic, Inc.
1989-Machine Lube System, CIP Gold River, B.C.

SaskPower Corporation
1993-Instrument Installation on Boundary Dam Power Station at Estevan, Sask.

Scott Paper Ltd.
1987-Two paper machine upgrades, New Westminster, B.C.

Shermco
2015-Instrument Installation For Imperial Oil’s Kearl Oilsands Expansion north of Ft. MacMurray, Alta.

Simplot Canada Ltd.
2001-Instrument Maintenance & Servicing At Brandon, Manitoba
1999-Instrument Maintenance & Commissioning at Brandon, Manitoba

Smith Electric Ltd.
1988-Macmillan Bloedel Ltd. #9 PM Powell River, B.C.

Sofame Technologies
2007-Instrument Installation for UBC Heat Recovery Project at Vancouver, BC

Spantec Constructors Ltd.
1995-Instrument Supply and Installation of SPX Project for Repap Manitoba Inc. at The Pas, Manitoba

State Electric Ltd.
1995-Instrument Installation on Terminal Project for Imperial Oil Ltd. at Port Moody, B.C.
1981–Control panels for Kelowna Sewage Treatment Plant in Kelowna, B.C.

Stella Jones
2015-Miscellaneous Maintenance Work For Lower Mainland Plant at New West, B.C.
2014-Miscellaneous Maintenance Work For Lower Mainland Plant at New West, B.C.
2013-Miscellaneous Maintenance Work For Lower Mainland Plant at New West, B.C.
2011-Miscellaneous Maintenance Work For Lower Mainland Plant at New West, B.C.
2009-Miscellaneous Maintenance Work For Lower Mainland Plant at New West, B.C.
2007-Miscellaneous Maintenance Work For Lower Mainland Plant at New West, B.C.
2005-Miscellaneous Maintenance Work For Lower Mainland Plant at New West, B.C.

Stothert Engineering Ltd.
1996-Instrument Material Supply for P.T. Indah Kiat Pulp & Paper at Jambi, Sumatra, Indonesia
1995-Instrument Material Supply for P.T.Indah Kiat Pulp and Paper at Pulp 8, Perawang, Indonesia
1994-Commissioning of Recaust Plants for P.T.Indah Kiat Pulp and Paper at Parawang & Jambi, Sumatra, Indonesia

Summit Electric
2019-Instrument Installation For Teck Coal’s Elkview Operations CHPP Coal Upgrade Project at Sparwood, B.C.
2019-Instrument Installation For New Gold’s New Afton Mine’s Gravity Recoverable Copper Project at Kamloops, B.C.
2019-Instrument Installation For Molson Coor’s New Brewhouse Cold Block Project at Chilliwack, B.C.
2017-Instrument Installation For Pretium’s Gold Mine north of Stewart, B.C.
2015-Instrument Installation For Kinder Morgan’s Pump Station at Kamloops, B.C.
2015-Instrument Installation For New Gold’s New Afton Mine Expansion at Kamloops, B.C.
2013-Instrument Installation For Taseko Mines Gibraltar GDP#3 at Williams Lake, B.C.
2011-Instrument Installation For New Gold’s New Afton Mine at Kamloops, B.C.

Sygnet Construction
1990-Instrument Installation for Skeena Cellulose CL02 Plant at Pr. Rupert, B.C.

The Electrician
2013-Supply of Control Panels for Ridley Terminals at Prince Rupert, B.C.
1990-Installation of Oxygen Plant for Canadian Liquid Air (L.A.E.C.) at Repap, Prince Rupert B.C.

T.L. & T. Electric Ltd.
1998-Instrument Installation on Effluent Package for Methanex Inc., at Kitimat, B.C.

Tradewind Electric Ltd.
1999-Instrument Supply and Install for Saanichton Waste Water Treatment Plant at Saanich, B.C.
1999-Instrument Supply, Install, Control Panel Supply for BCT Richmond Transit at Richmond, B.C.

TransCanada Pipelines
1997-Instrument Installation for New Compressors at Caron & Herbert, Saskatchewan

Trotter Morton
2019-Instrument Installation for the Dept. of National Defense’s B jetty Deconstruction at Esquimalt, B.C.

University of Alberta
2000-Instrument Supply & Installation for University of Alberta Stage 2 Additions At Edmonton, Alberta

University of British Columbia
1999-Numerous Incinerator Projects at Vancouver, B.C.

Ursel Constructors Ltd.
1988-Chemical Plant, at Pr.Albert Saskatchewan
1986-Instrument installation for Cominco, at Vade Sask.
1985-Instrument installation for Cominco, at Vade Sask.
1984-Instrument installation at PCS Lanigan at Lanigan, Saskatchewan

Vicar Electric
2004-Instrument Installation for Elk Falls Recovery Boiler #2 at Campbell River, B.C.

Weldwood of Canada Ltd.
1988-Instrument racks at Hinton,Alberta

Wellons Canada
2010-Instrument Installation For BCIT’s Lab Relocation At Burnaby, B.C.

Westcana Electric Ltd.
1999-Supply PLC Panel for Ridgeview RV Resort at Westside Kelowna, B.C.

Westcoast Energy Inc.
1999-Class I Div II Instrument Rack Supply for Ft. St. John, B.C.
1995-Station Control Panels and Other Panels for Northern B.C. natural gas comp. stations. at Ft. St. John (and others), B.C.
1994-SCP and UCP Control Stations Numerous Sites in British Columbia
1992-Control Console for Compressor Station at Mcleod Lake, B.C.

Western Forest Products Ltd.
1989-Digester installation Woodfibre, B.C.

Western Pacific Enterprises Ltd.
2019-Instrument Installation For the Capital Regional District’s McLoughlin Point Sewage Treatment Plant at Victoria, B.C.
2019-Instrument Installation For the Capital Regional District’s MaCaulay Point Pump Station at Saanich, B.C.
2019-Instrument Installation For the Capital Regional District’s Clover Point Pump Station at Victoria, B.C.
2019-Instrument Installation For Swisswater’s Expansion at Delta, B.C.
2019-Instrument Installation For MetroVancouver’s North Shore Conveyance Bridge Road Pump Station at North Vancouver, B.C.
2017-Instrument Installation For Seaspan’s Groundwater Treatment Plant at Richmond, B.C.
2017-Instrument Installation For Heemskirk’s Frac Sand Plant at Golden, B.C.
2015-Instrument Installation and Control Panel For the Alexandra District Energy Utility’s Phase 3 Pumphouse Expansion at Richmond, B.C.
2009-Instrument Installation For BC Hydro’s Cathedral Square Project At Vancouver, B.C. 2008-Instrument Installation and Control Panels Supply for Whistler Wastewater Treatment Plant at Whistler,BC
2008-Instrument Installation and Control Panels Supply for Whistler Wastewater Treatment Plant at Whistler,BC
2003-Instrument Supply and Installation and Control Panel Manufacturing for Capital Regional District’s UV Disinfection System at Langford, B.C.
2000-Instrument Installation & Commissioning for Island Co-Generation Plant At Campbell River, B.C.
1990-Instrument installation for L.A.E.C. (Canadian Liquid Air) at Port Mellon, B.C.

Western Pulp Partnership Ltd.
1989-Installation in various areas
1989-Supply of Field Racks Woodfibre, B.C.

Westwood Electric Ltd.
2015-Instrument Installation at Bell Mine in Granisle, B.C.
2013-Instrument Commissioning for Thompson Creek Metals at Mt. Milligan, B.C.
2013-Instrument Installation on CE702 for Mosaic Potash at Belle Plaine, Sask.
2012-Instrument Installation on CE301 for Mosaic Potash at Esterhazy, Saskatchewan
2011-Instrument Installation For Daishowa Marubeni Turbo Gen At Peace River, Alta.
2008-Instrument Installation for Tolko’s OSB Plant at Slave Lake, Alberta
2005-Instrument Installation & Calibration for Canfor’s OSB Plant. at Ft. St. John, B.C.
2002-Instrument Installation and Commissioning for Weyerhaeuser Dryden Pulp Mill’s Air Emissions Project (Boiler) at Dryden, Ontario
1994-Instrument Installation on Boiler for Scott Worldwide at Everett, Washington, U.S.A.
1992-Instrument Installation for Western Pulp Ltd. Partnership Secondary Effluent Package at Woodfibre, B.C.

Weyerhaeuser Canada Ltd.
2004-Supply of Process Control Panels for Miscellaneous Projects at Kamloops, B.C.
1995-Instrument Installation for numerous contractors on DCS, Black Liquor, and MC Pumps at Pr.Albert, Saskatchewan
1988-PDC Panel, Pr. Albert, Saskatchewan

Whelen Mechanical Installations Ltd.
1989-Soft Calender Cooling installation for Fletcher Challenge Canada at Elk Falls, B.C.
1980-Wet cell installation at MacMillan Bloedel Ltd. Port Alberni, B.C.

White Pine Electric Ltd.
2005-Instrument Installation for Bowater Corp’s Feed water Project at Thunder Bay, Ontario
2001-Instrument Installation for Bowater Corp’s Feed water Project at Thunder Bay, Ontario

Wright Schuchart Co. Ltd.
1989-R8 Module installation for Fletcher Challenge Canada at
Elk Falls, B.C.

Post a Comment